under construction · stage 5 of 7

Blue Line Phase 2A

BMRCL · 19.75 km, Central Silk Board to Krishnarajapura (KR Puram); part of Namma Metro Phase 2's Blue (Airport) Line. Construction began 2021-08. Also called Airport Line Phase 2A.

Current deadline
Mar 2027

original deadline not on record

Last checked
20 Sept 2026

re-checked every quarter

Not on record yet: a whole-project cost (only part figures so far), sanction date, original deadline. Missing data is shown, not guessed.

What's pending

As of 2025-06-30, physical progress on the combined Phase 2A+2B corridor was 52.5%, financial progress 55.89% (PropNewz). Expected operational around March 2027, alongside Pink Line's second section, per The Metro Rail Guy.

History

  1. Awarded

    BMRCL awarded both Phase 2A civil-works packages: ₹785.24 crore to Afcons Infrastructure (Package 1) and ₹623.55 crore to Shankaranarayana Constructions (Package 2). [1]

  2. sanctioned

    ₹785.24 cr Part figure: Package 1 civil works only (9.859 km, 6 stations) [1]

    Funder: state · FY 2021-22

    Context

    Package 1 civil works (9.859 km, 6 elevated stations: Central Silk Board, HSR Layout, Agara, Ibbalur, Bellandur, Kadubeesanahalli), awarded to Afcons Infrastructure

  3. sanctioned

    ₹623.55 cr Part figure: Package 2 civil works only (8.377 km, 7 stations) [1]

    Funder: state · FY 2021-22

    Context

    Package 2 civil works (8.377 km, 7 elevated stations: Kodibeesanahalli, Marathahalli, ISRO, Doddanekundi, DRDO sports complex, Saraswathi Nagar, KR Puram, plus a depot link and pocket track), awarded to Shankaranarayana Constructions

  4. revised cost

    ₹14,788.1 cr Part figure: Phase 2A and 2B combined (58.19 km), more than this project [2]

    Funder: state · FY 2025-26

    Context

    Combined Phase 2A+2B (58.19 km) total, not this project's 19.75 km alone — see project notes. Funding: ADB ₹2,410.79 cr, JICA ₹1,310.74 cr, PPP ₹800 cr, Karnataka State ₹4,074.34 cr, Centre ₹1,260.54 cr (these five figures do not sum to the headline total — see notes)

Sanctioned, released and spent are different things: an allocation is not evidence money was spent. Part figures cover one contract, loan or package and are never used as the project's cost.

Corrections to this page

Sources

medium confidence This page is based on news reports or an agency's own report, not yet an official document.

  1. Afcons & Shankaranarayana Awarded Bangalore Metro Phase 2A WorkThe Metro Rail Guy · news
  2. Bengaluru Airport Metro Phase 2B: KR Puram to Hebbal 38.44 km — Late 2026 to Early 2027 Operational TargetPropNewz · news
Notes and caveats

One money_entry here (₹14,788.101 cr) is the COMBINED cost for Phase 2A + 2B (58.19 km total), not this project's own 19.75 km alone — no source found apportions the figure between the two phases, so it is deliberately not split by estimate; it is flagged comparable_to_prior: false and excluded from this site's own derived "latest cost" figure for exactly that reason. To avoid double-counting in aggregate totals, the same combined figure is not repeated on blue-line-phase-2b; see that project's notes. Funding breakdown reported for the combined total: ADB ₹2,410.79 cr, JICA ₹1,310.74 cr, PPP ₹800 cr, Karnataka State ₹4,074.34 cr, Centre ₹1,260.54 cr — these five figures sum to about ₹9,856 cr, roughly ₹4,932 cr short of the ₹14,788.101 cr headline total; this gap is unresolved and flagged rather than corrected. Two package-level civil-works contracts are also on file (₹785.24 cr to Afcons, ₹623.55 cr to Shankaranarayana, both awarded 2021-05-25) — these are separate contracts for separate stretches of this phase, not additive into one project cost and not a substitute for the combined total above.

Report an error