Updates

Everything that has changed, newest first: developments on projects, corrections to our own records, and the notes from each quarterly re-check. Next quarterly re-check due January 2027. Subscribe: RSS · JSON

2026

  1. Correction C1Purple Line extension: Mysuru Road – Challaghatta

    Both are filed under fiscal year 2016-17, matching their approximate award date (October 2016). The amounts are unchanged.

    Previously: The Reach 2A (₹327 cr) and Reach 2B (₹332 cr) civil-works contract values were filed under fiscal year 2021-22, the year of the article that reported them.

    Raised by self-review; resolved using Metro Rail News

  2. Correction C2Blue Line Phase 2A

    No whole-project cost is on file yet. Both package contracts, and the combined Phase 2A+2B figure, are listed as part figures.

    Previously: Latest cost ₹623.55 cr and originally sanctioned ₹785.24 cr, with an overrun of −20.6%. These were two different civil-works packages compared with each other.

    Raised by self-review; resolved using The Metro Rail Guy

  3. Correction C3Blue Line Phase 2B

    No whole-project cost is on file yet. The depot contract is listed as a part figure.

    Previously: Latest and originally sanctioned cost ₹182.33 cr, which is the Airport depot civil-works contract only.

    Raised by self-review; resolved using Metro Rail News

  4. Correction C4Cauvery Water Supply Scheme Stage 5

    No whole-project cost is on file yet. Both JICA loans are listed as part figures.

    Previously: Latest and originally sanctioned cost ₹4,336 cr, which is the JICA loan for Phase 3(I) only.

    Raised by self-review; resolved using Japan International Cooperation Agency (JICA)

  5. Correction C5Pink Line (Kalena Agrahara – Nagawara)

    No whole-project cost is on file yet. Both Reach 6 contracts, the underground package and the trainset order are listed as part figures.

    Previously: Latest and originally sanctioned cost ₹578.7 cr, which is the original Reach 6 elevated-section contract only.

    Raised by self-review; resolved using The Metro Rail Guy

  6. Correction C6Purple Line extension: Mysuru Road – Challaghatta

    No whole-project cost is on file yet. Both reach contracts are listed as part figures.

    Previously: Latest cost ₹332 cr and originally sanctioned ₹327 cr, with an overrun of +1.5%. These were the Reach 2B and Reach 2A contracts compared with each other.

    Raised by self-review; resolved using Metro Rail News

  7. SanctionedBMTC electric bus fleet (PM E-DRIVE) · BMTC

    Karnataka Cabinet approved procurement of 4,500 electric buses for BMTC under the PM E-DRIVE scheme; state expenditure estimated at roughly ₹600 crore a year (~₹12,000 crore over 20 years), with a further ₹2,000 crore central loan sought for depot development.

    Source: Urban Acres · news

  8. Bid receivedBengaluru Business Corridor (Peripheral Ring Road) · BDA

    Two firms — Shankara Narayana Constructions and Vishwa Samudra Engineering — submitted bids for Package 1 (Tumkur Road–Bellary Road, 19.80 km, ~₹3,348 cr).

    Source: PropNewz · news

  9. Tender floatedNamma Metro Phase 3 · BMRCL

    BMRCL invited civil construction bids for the first 18.581 km of the Orange Line in three packages (JP Nagar 4th Phase–Kamakya, Hosekerehalli–Nagarbhavi Circle, Vinayaka Layout–BDA Complex Nagarbhavi), combined estimated cost ₹4,187.41 crore. Bid submission deadline 2026-02-25.

    Source: The Metro Rail Guy · news

2025

  1. Bid receivedHebbal–Silk Board Twin Tunnel Road · B-SMILE

    Financial bids opened; Adani Group emerged lowest bidder (L1) at ₹22,267 crore against the government's ₹17,698 crore estimate.

    Source: PropNewz · news

  2. Cost revisedNamma Metro Phase 3A (Hebbal – Sarjapur) · BMRCL

    Karnataka Cabinet approved a ₹2,920 crore cost reduction, bringing Phase 3A's estimated cost to ₹25,485 crore.

    Source: Nativeplanet · news

  3. SanctionedNamma Metro Phase 3 · BMRCL

    Karnataka Cabinet approved the ₹9,700 crore double-decker viaduct component covering both Phase 3 corridors.

    Source: The News Minute · news

  4. Section openedYellow Line (RV Road – Bommasandra) · BMRCL

    Yellow Line (RV Road–Bommasandra) inaugurated by the Prime Minister; commercial operations began the following day, 2025-08-11.

    Source: Dainik Jagran (thedailyjagran.com) · news

  5. Deadline revisedNamma Metro Phase 3 · BMRCL

    Completion deadline pushed to May 2031 — reported as a year later than originally planned — citing delays in inviting civil work tenders for the double-decker flyover design; cost reported up about 5%. (Publication date approximate — exact date not confirmed.)

    Deadline: May 2031

    Source: Deccan Herald · news

2024

  1. SanctionedNamma Metro Phase 3A (Hebbal – Sarjapur) · BMRCL

    Karnataka Cabinet approved Phase 3A (Hebbal–Sarjapur, 36.59 km) at an estimated cost of ₹28,405 crore. (Exact day not confirmed — reported as "December 2024".)

    Source: Nativeplanet · news

  2. Section openedGreen Line extension: Nagasandra – Madavar · BMRCL

    Nagasandra–Madavar extension became operational.

    Source: The Metro Rail Guy · news

  3. Section openedCauvery Water Supply Scheme Stage 5 · BWSSB

    BWSSB commissioned Cauvery Stage V, bringing 775 MLD of additional water supply toward 110 villages within BBMP limits.

    Source: Citizen Matters · news

  4. SanctionedNamma Metro Phase 3 · BMRCL

    Union Cabinet approved Phase 3 — 44.65 km, 31 stations, comprising the Orange Line (JP Nagar 4th Phase–Kempapura) and Grey Line (Hosahalli–Kadabagere).

    Source: Construction World · news

2023

  1. SanctionedBengaluru Suburban Rail Project · K-RIDE

    KfW Development Bank signed a €500 million (₹4,552 crore) loan agreement, plus a €4.5 million grant, with K-RIDE to finance Corridors 1 and 3.

    Source: Urban Transport News · news

  2. Section openedPurple Line extension: Baiyyappanahalli – Whitefield · BMRCL

    KR Pura–Whitefield section completed; the extension became fully operational (exact day not confirmed, month/year per The Metro Rail Guy).

    Source: The Metro Rail Guy · news

  3. Section openedPurple Line extension: Mysuru Road – Challaghatta · BMRCL

    Kengeri–Challaghatta section completed; the extension became fully operational (exact day not confirmed, month/year per The Metro Rail Guy).

    Source: The Metro Rail Guy · news

  4. AwardedBlue Line Phase 2B · BMRCL

    BMRCL awarded the ₹182.33 crore Airport Depot (Doddajala) civil works contract to a J Kumar Infraprojects–AIC Infrastructures joint venture.

    Source: Metro Rail News · news

  5. Section openedPurple Line extension: Baiyyappanahalli – Whitefield · BMRCL

    Baiyyappanahalli–KR Pura section opened (exact day not confirmed, month/year per The Metro Rail Guy).

    Source: The Metro Rail Guy · news

2022

  1. SanctionedCauvery Water Supply Scheme Stage 5 · BWSSB

    JICA signed a second ODA loan of JPY 37,068 million (reported as ≈₹2,391 crore) for Phase 3(II) water-supply and sewerage facilities.

    Source: Japan International Cooperation Agency (JICA) · agency report

  2. SanctionedBengaluru Business Corridor (Peripheral Ring Road) · BDA

    Karnataka Cabinet approved the Peripheral Ring Road project at an estimated cost of ₹21,091 crore under a 50-year build-operate-transfer concession.

    Source: Swarajya · news

2021

  1. StalledBengaluru Business Corridor (Peripheral Ring Road) · BDA

    Supreme Court order recorded that of the 1,810 acres 18.5 guntas notified for PRR Part 1, only 3 acres 21 guntas had actually been taken possession of; the Court directed the state government to hand over notified government land to BDA and directed BDA to simultaneously pass awards and take possession of notified land.

    Source: Supreme Court of India (via Indian Kanoon) · agency report

  2. Section openedPurple Line extension: Mysuru Road – Challaghatta · BMRCL

    Mysuru Road–Kengeri section opened (exact day not confirmed, month/year per The Metro Rail Guy).

    Source: The Metro Rail Guy · news

  3. Bid receivedPink Line (Kalena Agrahara – Nagawara) · BMRCL

    GR Infraprojects emerged lowest bidder among three qualified firms for the remaining Reach 6 work, at ₹364.87 crore.

    Source: The Metro Rail Guy · news

  4. AwardedBlue Line Phase 2A · BMRCL

    BMRCL awarded both Phase 2A civil-works packages: ₹785.24 crore to Afcons Infrastructure (Package 1) and ₹623.55 crore to Shankaranarayana Constructions (Package 2).

    Source: The Metro Rail Guy · news

  5. StalledPink Line (Kalena Agrahara – Nagawara) · BMRCL

    BMRCL terminated Simplex Infrastructures' ₹578.70 crore Reach 6 elevated-section contract citing poor progress — civil work had reached about 35-37% completion against a 27-month deadline that began in September 2017.

    Source: The Metro Rail Guy · news

  6. Section openedGreen Line extension: Yelachenahalli – Silk Institute · BMRCL

    Yelachenahalli–Silk Institute extension inaugurated.

    Source: The Metro Rail Guy · news

2020

  1. SanctionedBengaluru Suburban Rail Project · K-RIDE

    Central Government approved BSRP construction at a reduced cost of ₹15,767 crore, down from an earlier ₹18,621 crore estimate, with coach procurement shifted to a PPP leasing model.

    Source: Swarajya · news

2019

  1. AwardedPink Line (Kalena Agrahara – Nagawara) · BMRCL

    ITD Cementation India was awarded the ₹1,771.25 crore underground civil works package covering Tannery Road, Venkateshpura, Arabic College and Nagawara stations (4.59 km).

    Source: NBM&CW · news

2018

  1. SanctionedCauvery Water Supply Scheme Stage 5 · BWSSB

    JICA signed the first ODA loan agreement (Phase 3(I): JPY 81,060 million, of which JPY 45,000 million as tranche 1) for what BWSSB calls Cauvery Water Supply Scheme Stage V.

    Source: Japan International Cooperation Agency (JICA) · agency report

2011

  1. Section openedNamma Metro Phase 1 · BMRCL

    Reach 1 (6.7 km, Mahatma Gandhi Road–Baiyappanahalli) opened to the public — Namma Metro's first operational stretch.

    Source: The News Minute · news

Found something wrong?

Write to [email] with the project name and what you believe is correct. Every report is checked against our sources; where we were wrong, the fix is published here as a dated correction, not quietly edited away.