under construction · stage 5 of 7

Pink Line (Kalena Agrahara – Nagawara)

BMRCL · 21.39 km, 18 stations, part of Namma Metro Phase 2, opening in two sections Also called Namma Metro Phase 2 Pink Line.

Current deadline
Mar 2027

original deadline not on record

Last checked
20 Sept 2026

re-checked every quarter

Not on record yet: a whole-project cost (only part figures so far), sanction date, original deadline. Missing data is shown, not guessed.

What's pending

The first 7.5 km section (Kalena Agrahara–Tavarekere, 6 stations) is construction-complete and trial-run stage; commercial opening is awaiting the Government of India's confirmation of an inauguration date, as reported by Newskarnataka on 2026-09-03 and still unopened per that report as of 2026-08-26. The remaining Dairy Circle–Nagawara stretch is expected around March 2027, per The Metro Rail Guy.

History

  1. sanctioned

    ₹578.7 cr Part figure: Reach 6 elevated section contract only (original, terminated) [1]

    Funder: state · FY 2017-18

    Context

    Reach 6 elevated section (Dairy Circle Ramp–Kalena Agrahara, 7.5 km, 5 stations) awarded to Simplex Infrastructures; contract later terminated 2021-02-04 for poor progress (~35-37% complete against a 27-month deadline) — see events and the replacement contract below

  2. Awarded

    ITD Cementation India was awarded the ₹1,771.25 crore underground civil works package covering Tannery Road, Venkateshpura, Arabic College and Nagawara stations (4.59 km). [2]

  3. sanctioned

    ₹1,771.25 cr Part figure: One underground civil works package only (4.59 km, 4 stations) [2]

    Funder: state · FY 2019-20

    Context

    ITD Cementation India's underground civil works package: 4.59 km, 4 stations (Tannery Road, Venkateshpura, Arabic College, Nagawara), awarded "November 2019" per source (exact day not stated, as_of set to month start). This is one of at least two underground packages on the Pink Line — a second package (Dairy Circle–Langford Town–MICO Industries, won by Afcons Infrastructure) exists but its exact awarded value was not confirmed in this collection pass, so it is not recorded as a separate figure here.

  4. Stalled

    BMRCL terminated Simplex Infrastructures' ₹578.70 crore Reach 6 elevated-section contract citing poor progress — civil work had reached about 35-37% completion against a 27-month deadline that began in September 2017. [1]

  5. Bid received

    GR Infraprojects emerged lowest bidder among three qualified firms for the remaining Reach 6 work, at ₹364.87 crore. [3]

  6. sanctioned

    ₹364.87 cr Part figure: Reach 6 elevated section replacement contract only [3]

    Funder: state · FY 2021-22

    Context

    Replacement contract for the same Reach 6 elevated section, awarded to GR Infraprojects (lowest bidder, about 7.56% above BMRCL's own ₹339.21 cr estimate) after Simplex Infrastructures' contract was terminated

  7. sanctioned

    ₹405 cr Part figure: Seven additional trainsets only [4]

    Funder: state · FY 2024-25

    Context

    BEML variation order for 7 additional six-coach driverless trainsets specifically for the Pink Line (part of a larger, separate 53-trainset/₹3,177 cr system-wide BEML contract awarded 2023-08-07, which is not recorded here since it is not Pink-Line-specific)

Sanctioned, released and spent are different things: an allocation is not evidence money was spent. Part figures cover one contract, loan or package and are never used as the project's cost.

Corrections to this page

Sources

medium confidence This page is based on news reports or an agency's own report, not yet an official document.

  1. Bangalore Metro Terminates Simplex Infra's Pink Line ContractThe Metro Rail Guy · news
  2. BMRCL awarding 14-km metro contracts to ITD & Afcons (Pink Line underground packages)NBM&CW · news
  3. GR Infra Wins Bangalore Metro Pink Line's Pending WorkThe Metro Rail Guy · news
  4. Namma Metro: BEML to supply 7 more trains for Pink Line for Rs 405 crDeccan Herald · news
Notes and caveats

Corporation set to Central as a placeholder — this corridor spans Central/South/North; not yet mapped to wards. Money timeline is package-level, not a single project total: ₹405 cr for trainsets, plus individual civil-works contract values for the Reach 6 elevated section (originally ₹578.70 cr to Simplex Infrastructures, terminated 2021-02-04 at ~37% complete for poor progress, re-awarded at ₹364.87 cr to GR Infraprojects) and one of the underground packages (₹1,771.25 cr, ITD Cementation). A Wikipedia-reported aggregate figure of ₹5,925.95 cr for all underground tunneling packages combined, and a ₹9,508.33 cr total-line figure covering all phases, are not recorded here as this site has not independently verified either total against a primary or directly-fetched source — only the individually-confirmed package values above are on file. No figure exists yet for the remaining underground package (Dairy Circle–Langford Town–MICO Industries, Afcons Infrastructure).

Report an error